Target build start dateTarget end date |
Spring 2022
Summer 2024
|
Current activity
December 2020
Following the move to a new combined scheme, the design work has required a fresh start.
We are currently looking at the 1:500 floor plans, to agree the basic layout of the clinical areas. We are using the principles agreed during the design phase for TUEC, and the additional learning from COVID to inform these decision. If you would like to know more, please get in touch with Clare Bosanko, Vicky Carter, Higgi or Ian McCarthy.
Following the move to a new combined scheme, the design work has required a fresh start.
We are currently looking at the 1:500 floor plans, to agree the basic layout of the clinical areas. We are using the principles agreed during the design phase for TUEC, and the additional learning from COVID to inform these decision. If you would like to know more, please get in touch with Clare Bosanko, Vicky Carter, Higgi or Ian McCarthy.
TUEC Timeline - historical
February 2020
Interior design meeting - the focus is on using colour to aid way finding for patients and relatives in the new department.
Interior design meeting - the focus is on using colour to aid way finding for patients and relatives in the new department.
November 2019
1:200 plans signed off
1:200 plans signed off
October 2019
User groups established to consider the stage 3 designs:
User groups established to consider the stage 3 designs:
- Entrance/Front of house
- Assessment (streaming / triage / care initiation)
- Ambulance entrance / FLIC / Major Incident
- Adult treatment area
- Resus
- Adult SDEC (AAU)
- Paediatric ED
- Staff areas / Admin
Autumn 2019
A round of meetings considering the way the different areas of the department are laid out and rooms designed.
Spring 2019
Stakeholder meetings to look at initial design proposals from the architects, involving ED, paediatric and AAU staff as well as representatives from the wider hospital
December 2018
Successful funding application awarded to provide £29.7 million pounds.
Summer 2018
Stakeholder meetings with key areas to agree Schedule of Accommodation.
December 2017
Selection of Principle Supply Chain Partner, Kier, under P22 arrangements.
June 2017
Trust board agreed to support development of the Strategic Outline Case into a Business Case.
A round of meetings considering the way the different areas of the department are laid out and rooms designed.
Spring 2019
Stakeholder meetings to look at initial design proposals from the architects, involving ED, paediatric and AAU staff as well as representatives from the wider hospital
December 2018
Successful funding application awarded to provide £29.7 million pounds.
Summer 2018
Stakeholder meetings with key areas to agree Schedule of Accommodation.
December 2017
Selection of Principle Supply Chain Partner, Kier, under P22 arrangements.
June 2017
Trust board agreed to support development of the Strategic Outline Case into a Business Case.